2017 Renovation Status

February 28, 2017

Brando Suites Bora Bora (Two-Bedroom Suites)

As expected, Suites 1 and 2 are now fully covered.

The walls of Suites 3 are being assembled, and it should be covered by the end of March. The piling of Suite 4 is completed, the wall assembly will begin, and the suite is estimated to be covered by the end of April.

May to November will be the time for inside work in the suites: electricity, plumbing, painting, and furnishings with approximately zero noise.

All four Suites will be ready for sale by December 1, 2017. A selection of commercial material is already available under this link should you need more information: artist renderings and floor plans.

Pool Villas and Premium Pool Villas

The renovation schedule is also respected for the addition of private pools to the 10 overwater villas located in the southern branch of the resort.
The work is still estimated to be finished by June 15, 2017, and those units will be available for sale starting July 1, 2017.

A selection of commercial material is already available under this link should you need more information: artist renderings and floor plans.



Guest Experience

We are glad to observe a maintained high level of guest satisfaction, with little to no comment on the current renovations (see our TripAdvisor page, or IHG comments).

All villas surrounding the renovations areas have been closed for sale to ensure our guests the best experience possible. Construction material is hardly visible from the main beach, which allows an unobstructed view of Mount Otemanu and a seamless tropical luxury vacation for our guests.

Please kindly note that the construction compensation of 6 000 CFP per night per villa will end on June 30, 2017.


January 30, 2017



Brando Suites Bora Bora (Two-Bedroom Suites)

Suites 1 and 2 will be completely covered by February 1st.


As for Suite 3, the assembly of walls is currently taking place and will be entirely covered by March 10th. The piling of Suite 4 will be completed by February 6th and is expected to be fully covered by the end of April.


From May through November 30, 2017, we will be working inside the Suites on electricity, plumbing, painting, and furnishings with approximately zero noise. The Suites will be ready for sale by December 1, 2017.

Pool Villas and Premium Pool Villas

As previously announced, 10 infinity swimming pools will be added to existing villas on the South branch of the resort. The work started on January 16, 2017, and will be completed by June 15, 2017. Those units will be available for sale starting July 1, 2017. We always respect our time schedule, and this two-week buffer will allow us to be fully ready.

By late April 2017, the two-story cranes over a barge will be gone.

Our construction compensation of 6 000 CFP per night per villa will end on June 30, 2017.

We are also planning to organize a photo shoot of the resort as soon as the villas are ready. In the meantime, you will find HERE some artist renderings as well as floor plans of these new units.